Preparing Practice Exam…
Please wait a moment while the system generates the exam questions, answers, and study session.
Please wait a moment while the system generates the exam questions, answers, and study session.
PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Resource-constrained scheduling creates a schedule where resource availability is the overriding constraint. When resource demand exceeds supply, activities are delayed until resources become available, even if this extends the project beyond the CPM-calculated minimum duration. The resulting schedule is more realistic because it reflects actual resource capacity. The critical chain (resource-dependent critical path) may differ from the traditional CPM critical path.