PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Schedule sensitivity analysis determines which activities have the greatest impact on overall schedule uncertainty. Typically performed alongside Monte Carlo simulation, it measures the correlation between each activity's duration variation and the project completion date variation. Activities with high sensitivity (high correlation) are the biggest drivers of schedule risk and should receive the most management attention for risk mitigation. Results are often displayed as tornado diagrams.