PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A schedule health assessment evaluates the technical quality and reliability of the project schedule. Key indicators include: logic integrity (no broken logic or dangling activities), missing predecessors or successors, constraint usage (excessive constraints mask logic issues), float distribution (negative float, unrealistic float), critical path validity (single longest path vs fragmented critical paths), relationship type distribution, and high-duration activities without detail.