Question 50 of 52
Free Preview · 52 of 172 · questions 1–52 of 172 are free. Sign up free to sync your progress across devices.
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Resource-constrained scheduling creates a schedule where resource availability is the overriding constraint. When resource demand exceeds supply, activities are delayed until resources become available, even if this extends the project beyond the CPM-calculated minimum duration. The resulting schedule is more realistic because it reflects actual resource capacity. The critical chain (resource-dependent critical path) may differ from the traditional CPM critical path.