Not c as the design is already approved
The PM must inform the client of the issue, present the agreed-upon solution, and submit a formal change request for approval through the project's change control procedures.
The answer is B. The team and owner 'already agreed' to revise the design. At this point, doing another PoC (C) is redundant and skips the required administrative step. PMI prioritizes following the established change control procedure (B) once a decision to change a baseline is reached.