Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
When a customer claims a requirement is missing, the first step is to refer to the Requirements Traceability Matrix (RTM) to objectively analyze whether the requirement was captured, approved, and delivered.
A. Refer to the requirements traceability matrix
A. Refer to the requirements traceability matrix