Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- VAC = BAC - EAC. First, calculate EAC = BAC / CPI = $1,000,000 / 0.80 = $1,250,000. Then, VAC = $1,000,000 - $1,250,000 = -$250,000. The negative VAC indicates the project is expected to be $250,000 over budget at completion if the current cost performance trend continues.