Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Answer: → C. Add the delay to the issue log and work with the vendor for a resolution that will bring the schedule back on track → Flow: [Procurement Management > Control Procurements] → [Integration Management > Monitor and Control Project Work] → [Issue Management (Issue Log)] → [Manage Stakeholder Engagement (Vendor)] + [Schedule Management > Control Schedule] → [Perform Integrated Change Control (if needed)] → [Risk Management (updates)] → First document the realized delay as an issue, then collaborate directly with the vendor (as a key stakeholder) to find a mutually acceptable corrective action.
As this is no longer a Risk, rather an Issue so we have to update in the Issue log and then work with the vendor how to fix this mess!
AI said A