Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Cost Variance (CV) = EV - AC. When CV is negative, the Actual Cost (AC) exceeds the Earned Value (EV), meaning the project has spent more money than the value of work completed. In other words, the project is over budget. A positive CV would indicate the project is under budget.