Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Correct answer: D. Perform Integrated Change Control. Takeaway: The team has already identified an alternative solution that will increase cost. Any option that affects cost, schedule, scope, or resources must go through Integrated Change Control before being approved or implemented. PMI expects the project manager to follow the formal change‑control process whenever a change has an impact on the baselines — even if the project is under budget.