Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Correct answer: B. Negotiate a contract and form a partnership with a local authority for medical and security support services. Takeaway: The project is being delivered in a dangerous location, across multiple sites, with parallel iterations — meaning the risk exposure is continuous and widespread. PMI expects the project manager to implement risk responses that reduce the probability and impact of harm, not just document or partially mitigate them. The strongest, most appropriate action is to secure professional, local medical and security support, which directly addresses the high‑level risks.