- Fast tracking increases risk because overlapping activities that were originally sequential means that later activities start before the outputs of earlier activities are finalized. If earlier activities produce unexpected results, the overlapping work may need to be redone. Increased cost from adding resources is the primary risk of crashing, not fast tracking.