- CPI (Cost Performance Index) of 0.85 means the project is getting only $0.85 of value for every $1 spent — it is over budget. SPI (Schedule Performance Index) of 1.10 means the project has accomplished 110% of the planned work — it is ahead of schedule. So the project is over budget but ahead of schedule.