Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Why the other options are incorrect: B. Cost estimates and cost forecasts → These are more relevant to Quantitative Risk Analysis and Cost Management, not qualitative assessments. C. Risk management plan and basis of estimates → While the risk management plan is correct, basis of estimates is more useful in cost control and not a primary input for qualitative risk analysis. D. Assumption log and project charter → The project charter is important during initiation, not during risk analysis.
The risk management plan outlines the strategy for managing risks throughout the project, including the approach to identifying, assessing, and responding to risks.
A. 11.3.1.1, and 11.3.1.2.