Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Qualitative risk analysis prioritizes risks by assessing their probability of occurrence and impact on project objectives, typically using a probability-impact matrix. Risks are categorized as high, medium, or low priority. This process is usually quick, cost-effective, and performed on all identified risks. Quantitative risk analysis uses numerical methods like Monte Carlo simulation and decision trees for deeper analysis of the highest-priority risks.