- Expected Monetary Value (EMV) is calculated by multiplying the probability of occurrence by the impact: EMV = Probability x Impact = 0.30 x $100,000 = $30,000. EMV is used in quantitative risk analysis and decision tree analysis to evaluate risks numerically. For threats, EMV is negative (a cost); for opportunities, EMV is positive (a benefit). The EMV helps in making informed decisions about risk responses and contingency reserves.