Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The outputs from creating a Work Breakdown Structure (WBS) are: the WBS itself, a WBS Dictionary, the Scope Baseline, and project documentation updates.
See 5.4.3 Create WBS: Outputs
B - pg 570 6th ed 1. Scope Baseline 2. Project Documents Updates