Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A Gantt chart (bar chart) displays project activities as horizontal bars plotted against a timeline. It shows start dates, end dates, and durations for each activity, making it easy to visualize the project schedule. While some modern Gantt charts can show dependencies and the critical path, their primary purpose is providing a visual timeline of activities. Network diagrams are better for identifying the critical path.