Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Fast tracking involves performing activities or phases in parallel that would normally be done in sequence. For example, starting construction before all designs are finalized. While fast tracking can shorten the schedule, it increases risk because rework may be needed if earlier activities change. Crashing, by contrast, adds resources to shorten activity durations.