Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
This question is clearly implying an agile environment, and the only one of these that references agile techniques is B.
This approach focuses on establishing clear channels for managing changes through a robust change control process. Having focal points for key subjects aids in directing communications to address uncertainties effectively. Additionally, promoting formal and transparent communication helps in managing expectations and ensuring stakeholders are informed. While options like involving stakeholders in project meetings (A), inviting customers to certain meetings (B), or using social networking for engagement (C) have their merits, in an environment with uncertain requirements, having a structured change control process and transparent formal communication channels is crucial to manage changes and keep stakeholders informed of developments and adjustments in the project.
Per the PMBOK in an agile/ adaptive environment one should co-locate team members as much as possible and have frequent checkpoints