Certified Associate in Project Management · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A lead allows an acceleration of the successor activity. With a 5-day lead on a Finish-to-Start relationship, Activity B can start 5 days before Activity A finishes. This overlaps the two activities to compress the schedule. In contrast, a lag would add a waiting period. Leads are represented as negative values in scheduling software (e.g., FS -5 days).