Professional Scrum Product Owner II (PSPO II) · Scrum
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Weighted Shortest Job First (WSJF) ranks work by Cost of Delay divided by job size. When jobs are similar in size, the one with higher Cost of Delay (Item A — $100K loss if delayed) ships first. PSPO II tests value-based prioritization that considers urgency, not just steady-state value.