Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Answer: B. Expert judgment ✅ Why: If a key stakeholder does not accept the KPI results, the PM can use expert judgment to validate and interpret the performance data. A ❌ Change control — for approved changes. B ✅ Expert judgment — helps resolve disagreements about KPI interpretation. C ❌ Autocratic — not appropriate for stakeholder disagreement. D ❌ Context diagram — used to understand system boundaries/interactions.