Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The Power/Interest grid recommends keeping stakeholders with high power and low interest satisfied. These stakeholders can significantly impact the project but are not deeply interested in day-to-day details. The strategy is to keep them satisfied with key information and address concerns promptly, without overloading them with unnecessary detail.