Assess the amount of time before the risk can impact one or more project objectives --> Proximity Assess if the risk is related to other individual project risks --> Connectivity Assess how quickly the risk response needs to be implemented in order to be effective --> Urgency Assess how long after a risk has occurred before its impact is discovered --> Dormancy
Answer 1 – Proximity, 2-Connectivity, 3- Urgency, 4-Dormancy