Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
The root cause of the team's inefficiency is that they are manually generating multiple reporting formats for the same project updates. This indicates a lack of structure in how communication is managed. The Strategy: By segmenting the communications, the project manager categorizes stakeholders based on their specific information needs, power, and interest. The Outcome: Once these standard segments are defined in the Communications Management Plan, the team can automate the reporting process.
C is correct
C. Segment the types of communications to be delivered to different stakeholder