PERT is E = O + 4 M + P divides by 6 E is already in the question as 5 months , And O optimistic time ( which is known as best time ) Thus $5000 x 4 months = $20,000 Therefore 2 Engr is $1,400 + $1,600 + $2000 = $
It cannot be B
Why B? anyone can explain?