Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
B. Add the activist group to the list of stakeholders and analyze the impact they may have on project delivery
B . need to consider Activst group also an important stakeholder
B. Add the activist group to the list of stakeholders and analyze the impact they may have on project delivery