Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Protect the resource(in conflict) through negotiation first before taking any other action. Example : Functional manager pulling your only SME? → Design Negotiation Strategy first!
D. Design a negotiation strategy for this situation
D. Designing a negotiation strategy allows the project manager to discuss with the manager the importance of the SME to the project's completion, and perhaps they can reach a compromise. For instance, the SME might split their time or prioritize the most critical tasks first. It's a proactive approach that addresses the immediate need without escalating or introducing potential delays.