Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
B is better. Publicly discussing a member's performance issue in a team meeting might negatively impact morale and trust. It could lead to defensiveness or discomfort among team members, which might not be conducive to open and honest communication.
PMBOK 6th and 5th It was common for project managers to discuss with each team member individually and provide feedback. PMBOK 7th The project manager should play a problem-solving role to enhance collaboration among the entire team. It is more appropriate to achieve continuous improvement through team-level discussion and collaboration. "C"
Transparency. Being transparent about how people think, make choices, and process information helps others understand and share their own processes. This can also be transparent about bias.