Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Why C is Best: Directly addresses the need for speed ("released fast to the users") in a competitive landscape. Incremental delivery supports early value realization and benefits management.
The key point is "The goal of the project is to extend a desktop application with a mobile application module. " which means there is the desktop version of product in the market, and the company need mobile version. The requirements and scope are defined, the most important thing is how to deliver the mobile version fast. So the answer C is the one which can increase speed.