Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Managing project compliance means confirming compliance requirements, determining the approach and actions to address them, and measuring the extent to which the project complies. A mandatory standard therefore enters scope as a requirement with testable acceptance criteria and an ongoing compliance measure, rather than a constraint reviewed periodically. Treating a mandatory standard as a risk implies it might not apply, and logging it as an assumption hands ownership to someone outside the project.