Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Answer: → B. Train the team to first find the minimum viable product (MVP) that will deliver value to the customer. → Flow: [Uncertainty Domain > Iterative Development] → [Scope + Value Prioritization] → [Define & Build MVP] → [Customer Validation / Feedback Loops] → [Pivot / Iterate / Scale based on Data] → [Risk Reduction + Early Value Realization].
To avoid the problem of overspending upfront, B (MVP thinking) helps control scope and investment from the very start.
B is good