Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Regulatory compliance is mandatory and cannot be ignored. The project manager should first assess the impact of the regulatory change on project deliverables, scope, schedule, and cost. Then, a change request should be submitted through integrated change control to formally incorporate the required modifications. Project work should continue on unaffected areas.