Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- WIP (Work in Progress) limits are a core Kanban principle designed to improve flow, reduce context switching, and identify bottlenecks. When a WIP limit is exceeded, the team should stop starting new work and focus on finishing existing items. They should also investigate why the limit was exceeded to prevent recurrence. Raising the limit defeats its purpose.