Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Answer: → B. Planned and scheduled tasks and work packages to overcome geographical and time zone challenges. → Flow: [Integration > Develop Project Management Plan] → [Resource Management > Plan Resource Management] → [Schedule Management > Develop Schedule (Time Zone Adjusted Calendars + Sequencing + Leads/Lags)] → [Communications Management > Plan Communications] → [Team Performance Domain > Develop/Manage Team (Virtual Collaboration)] → [Monitor & Adapt] → Prevent stalls through proactive planning.
Je pense que seul une bonne planification basé sur les différentes heures permet de limiter le challenge du fuseau horaire
B is the right answer, since asynchronous collaboration seems to be an issue, effective planning and assignment of tasks will be the best approach.