Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
Answer: → C. Connect with every location and check their preferred methods of communication. → Flow: [Stakeholder Performance Domain > Plan Stakeholder Engagement] → [Communications Management > Plan Communications Management] → [Resource Management > Plan Resource Management] → [Team Performance Domain > Develop Team (Virtual/Global)] → [Manage Communications + Ground Rules + Tailored Tools] → [Ongoing Monitoring & Adaptation] → Effective distributed collaboration.
In this situation, I believe the best solution would be to reach out to the various team members in the various location and inquire about their preferred communication style as this shows effective team leadership and management on the part of the PM
C connect with every location