Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- A data point beyond the control limits indicates the process is out of statistical control and is due to an assignable (special) cause rather than normal variation. The project manager should investigate the root cause of this variation and take corrective action. Widening control limits masks the problem; doing nothing ignores a quality signal.