financial risks + frequently check + strength and efficiency + risk management process This is asking how to check whether the risk management process is working well. That is a risk audit.
Risk audits are used to evaluate how well risk management processes are being implemented and how effective they are. A : Used to identify risks, not to assess the effectiveness of the risk process. C : Tracks assumptions and constraints, not how well risk management is working.
D- The audit meeting would the best case Scanio to better analyze and solve the current financial risk