Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Fast tracking involves performing activities in parallel that were originally planned sequentially. By overlapping activities, the schedule is compressed. However, fast tracking increases risk because activities that normally benefit from sequential output are now running concurrently, which can lead to rework if early outputs change.