Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Work performance data consists of raw observations and measurements collected during execution (e.g., 40% complete, $50,000 spent). Work performance information is analyzed data with context (e.g., SV = -$20,000, behind schedule). Work performance reports are formatted communications for stakeholders (e.g., status reports, dashboards). Each builds on the previous level.