Project Management Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The work package is the lowest level of the WBS. It represents a deliverable or project work that can be reliably estimated, scheduled, monitored, and controlled. Activities (the tasks needed to complete work packages) are defined separately in the activity list and are NOT part of the WBS itself.