Answer: A. Evaluate the situation and identify ways to compress the schedule without impacting baselines. ✅ Why: The first module took 45 days instead of 35, so the PM should first analyze the cause and impact before taking action. A ✅ Evaluate and find schedule-compression options. B ❌ Overtime is premature. C ❌ Don't request a baseline change before analysis. D ❌ Scope creep isn't indicated.
Why D is correct Scope verification is the correct first action because: A 10‑day overrun on a single module suggests unplanned work, unclear requirements, or gold‑plating. If scope creep is present, compressing the schedule or requesting changes won’t solve the root cause. Getting the project back on schedule requires confirming the team is only delivering what was originally approved. This aligns with PMI best practice: validate scope before adjusting schedule.