PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Free float is the amount of time an activity can be delayed without delaying the early start of any immediate successor activity. Total float is the amount an activity can be delayed without delaying the project completion date. Free float is always less than or equal to total float. Free float belongs exclusively to the individual activity, while total float is shared among activities on the same path. This distinction is important for scheduling decisions.