PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Fast-tracking involves performing activities in parallel that would normally be done sequentially (e.g., starting detailed design before requirements are fully finalized). While it can reduce duration without adding cost, it introduces risks including rework if predecessor outputs change, increased coordination complexity, potential quality issues from incomplete information, and resource conflicts from overlapping activities. Only activities with discretionary dependencies can be fast-tracked.