You are right on the explanation.......
AC=440,000, PV=447,000 (i.e. 745000x0.6)
To better explain the math, you multiple $745,000 by .75 (since you are supposed to be 3rd milestone) to get $558,750. Then you take what you spent already; $440,000 and divide that by $558,750 to get .787472 = .80