PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Resource leveling resolves resource over-allocation by delaying activities until resources are available, potentially extending the project duration and changing the critical path. Resource smoothing adjusts activities only within their available total float to reduce resource demand peaks without extending the project end date. Leveling prioritizes resource constraints over time, while smoothing prioritizes the project end date over optimal resource utilization.