PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- Schedule Performance Index (SPI) is calculated as EV/PV (Earned Value divided by Planned Value). An SPI of 0.9 means the project has completed only 90% of the work value planned for this point in time — it is behind schedule. SPI < 1.0 indicates behind schedule, SPI = 1.0 indicates on schedule, and SPI > 1.0 indicates ahead of schedule. SPI is a key metric for schedule performance monitoring.