PMI Scheduling Professional · PMI
Select one answer.
Written by other learners. Comments can disagree with the marked answer — check the official documentation when in doubt.
- The forward pass is the first step in CPM calculations, moving forward through the network diagram from the project start to determine the earliest possible start (ES) and earliest possible finish (EF) for each activity. ES is determined by the latest EF of all predecessors, and EF = ES + Duration. The forward pass establishes the minimum project duration by identifying the latest EF in the network.