- Assumptions are factors that are considered true without proof or verification. If an assumption proves incorrect, it can trigger or increase risk. For example, assuming a key resource will be available is an assumption; if that person is reassigned, it becomes a realized risk. Assumptions and risks are closely related, and both can affect any project objective.